Capital Projects
MENU
LOGIN
SEARCH
Menu Button
MENU
City Logo
Search Button
SEARCH

Projects Under Construction

Click here for information about Roads Program projects



City Project #18-69 - Surface Water Distribution System Improvements

The Project consists of constructing a 2.3 million gallon concrete tank, 12 million gallon per day pump station and building, detention basin and storm water pump station, 12,000 linear feet of 16-inch to 54-inch diameter potable water pipeline and appurtenances, 2,500 linear feet of 15-inch storm drain pipeline and manholes, three pressure reducing valve vaults, pavement improvements, associated grading, structural mechanical, electrical, and instrumentation equipment, and all work necessary to provide a complete and operational facility. A pre-bid conference will be held at 10:00 a.m., local time on Wednesday June 16, 2021 through a video conference and a second pre-bid conference will be held at 10:00 a.m., local time on Monday June 28, 2021 through a video conference. The pre-bid conference is mandatory and a bidder who fails to attend a pre-bid conference may be disqualified from bidding. Bidders only need to attend one pre-bid conference. To obtain video conference login information email all of the following contacts at least 24 hours prior to the pre-bid meeting date and time: Jonathon Marshall jpmarshall@carollo.com, Darren Baune dbaune@carollo.com, and Andrew Coulter acoulter@carollo.com to request the login information.

Construction Duration: Work for the following project is schedule to begin on or about Friday, September 10, 2021 and estimated to complete on or around Wednesday, November 15, 2023.
Contractor: Mountain Cascade
Traffic Delays: Pipeline construction will include Zeering Road from Quincy Road to Wellington, Quincy Road from Zeering Road to Sebastian, Monte Vista Ave. from Quincy to Berkeley. Lane closures will be in effect for work on Monte Vista Ave. and Zeering Road. Road closures will be in effect for Quincy Road (local traffic only). In addition, the Stanislaus Regional Water Authority (SRWA) will be installing pipeline to the City's terminal tank site on Berkeley Road (north of City limits), on E. Taylor Road between Berkeley and Quincy, and on Quincy Rd. to the City's terminal tank site located at 3500 N. Quincy Road. For more information, please visit Stanislaus Regional Water Authority and Turlock Water
Technical Contact: Project Manager, Stephen Fremming, ph: 209-668-5417, sfremming@turlock.ca.us

City Project #20-032 - Chemical System Upgrades Project at RWQCF

The Project consists of constructing the following components at the Regional Water Quality Control Facility: 1. Demolition of the existing Chlorine Gas disinfection system. 2. Installation of a new Sodium Hypochlorite disinfection system. 3. Demolition and installation of a new Coagulant chemical system. 4. Demolition and installation of a new Dechlorination system. 5. Additions and modifications to yard piping system. 6. Additions and modifications to electrical systems. 7. Additions and modifications to instrumentation systems. 8. Repair and reconstruction to existing facilities affected by the work and all work necessary to render the facility complete and operational.

Construction Duration: Work for the following project is schedule to begin on or about Monday, June 6, 2022 and estimated to complete on or around Wednesday, November 15, 2023.
Contractor: Pacific Infrastructure Corporation
Traffic Delays: None
Technical Contact: Project Manager, Stephen Fremming, ph: 209-668-5417, sfremming@turlock.ca.us

City Project #20-027A - City Wide Chlorination

The work consists, in general, of: constructing new chlorination systems at fifteen (15) active wells and three (3) water storage tank/pumping stations within the City’s water system.

Construction Duration: Work for the following project is schedule to begin on or about Wednesday, February 17, 2021 and estimated to complete on or around Thursday, August 31, 2023.
Contractor: Clark Bros. Inc.
Traffic Delays: none
Technical Contact: Project Manager, Stephen Fremming, ph: 209-668-5417, sfremming@turlock.ca.us

City Project #20-013R - Water and Sewer Main Extensions Golden State Blvd

The work consists, in general, of: demolition, shoring utility potholing, traffic control, trenching, installation of water mains and lateral pipes, valves, fittings, fire hydrants, installation of sewer mains and manholes, paving, curb, gutter and sidewalk.

Construction Duration: Work for the following project is schedule to begin on or about Tuesday, January 17, 2023 and estimated to complete on or around Friday, September 1, 2023.
Contractor: Rolfe Construction, Inc.
Traffic Delays: Pipeline construction will include Golden State Blvd. from Atherstone Road to about half a mile north of Taylor Road (near Price Ford of Turlock). Lane closures will be in effect on Golden State Blvd and Taylor Road.
Technical Contact: Project Manager, Janine Lee, 209-668-6035, jlee@turlock.ca.us

City Project #22-037 - Fire Station No. 32 & 33 Reroof

Roof repair of Fire Station No. 32 (located at 791 S Walnut Rd, Turlock, CA 95380) and Fire Station No. 33 (located at 501 E Monte Vista Ave, Turlock, CA 95382). An optional pre-bid meeting will be held on Thursday, March 30, 2023 at 10:30 AM at Turlock Fire Station No. 33.

Construction Duration: Work for the following project is schedule to begin on or about Monday, June 12, 2023 and estimated to complete on or around Monday, November 6, 2023.
Contractor: Pac Shield Roof Services, Inc.
Traffic Delays: None.
Technical Contact: Project Manager, Charlotte Calvario, 209-668-6029, ccalvario@turlock.ca.us

City Project #20-002 - SW Quadrant Road Rehabilitation

The work consists, in general of: remove existing improvements, relocate fences, install access ramps, curb, gutter, sidewalk, earthwork, grading, scarification, grinding, HMA paving, street light, striping, minor storm drain improvements and other associated work.

Construction Duration: Work for the following project is schedule to begin on or about Monday, July 10, 2023 and estimated to complete on or around Friday, September 29, 2023.
Contractor: George Reed
Traffic Delays: Road closures with detours will be required.
Technical Contact: Randall Jones, RJones@turlock.ca.us

City Project #23-025 - Street Tree Replacement 2023

Installation of street trees in various locations throughout the City.

Construction Duration: Work for the following project is schedule to begin on or about Saturday, September 30, 2023 and estimated to complete on or around Friday, December 1, 2023.
Contractor:
Traffic Delays:

City Project #19-51B - Columbia Pool Improvements

The work consists, in general of: Install pool, pool chemical and mechanical equipment, pool piping, pool decking, earthwork and grading, flatwork concrete, construct a chemical and mechanical building shell, prepare base and coordinate with Public Restroom Company building installation, paving, CMU wall, steel fencing, safety lighting, water services, fire hydrant assembly, storm drain improvements, sewer lines, cleanouts, and manholes, gas line, arbors, benches, drinking fountains, landscaping and irrigation improvements, and other associated work.

Construction Duration: Work for the following project is schedule to begin on or about Wednesday, January 3, 2024 and estimated to complete on or around Sunday, June 30, 2024.
Contractor: Bobo Construction
Traffic Delays: None
Technical Contact: Randall Jones

City Project #23-049 - Senior Center Window Replacements

Remove and replace all windows at the Senior Center. An optional pre-bid meeting will be held on Thursday, December 14th at 8:30 AM in the Senior Center located at 1191 Cahill St, Turlock, CA 95380.

Construction Duration: Work for the following project is schedule to begin on or about Monday, April 15, 2024 and estimated to complete on or around Friday, May 3, 2024.
Contractor: Glass & Window Services
Traffic Delays: None.
Technical Contact: Project Manager, Charlotte Calvario, 209-668-6029, ccalvario@turlock.ca.us

For more information or concerns about capital projects, please contact:

Engineering Division
156 S. Broadway, Ste. 150
Turlock, CA 95380
(209) 668-5520
engineering@turlock.ca.us
Monday - Friday, 8AM - 5PM






Icons made by Freepik from www.flaticon.com is licensed by CC 3.0 BY



Top