Projects Under Construction

City Project #18-69 - Surface Water Distribution System Improvements
The Project consists of constructing a 2.3 million gallon concrete tank, 12 million gallon per day pump station and building, detention basin and storm water pump station, 12,000 linear feet of 16-inch to 54-inch diameter potable water pipeline and appurtenances, 2,500 linear feet of 15-inch storm drain pipeline and manholes, three pressure reducing valve vaults, pavement improvements, associated grading, structural mechanical, electrical, and instrumentation equipment, and all work necessary to provide a complete and operational facility. A pre-bid conference will be held at 10:00 a.m., local time on Wednesday June 16, 2021 through a video conference and a second pre-bid conference will be held at 10:00 a.m., local time on Monday June 28, 2021 through a video conference. The pre-bid conference is mandatory and a bidder who fails to attend a pre-bid conference may be disqualified from bidding. Bidders only need to attend one pre-bid conference. To obtain video conference login information email all of the following contacts at least 24 hours prior to the pre-bid meeting date and time: Jonathon Marshall jpmarshall@carollo.com, Darren Baune dbaune@carollo.com, and Andrew Coulter acoulter@carollo.com to request the login information.Construction Duration: Work for the following project is schedule to begin on or about Friday, September 10, 2021 and estimated to complete on or around Saturday, August 5, 2023.
Contractor: Mountain Cascade
Traffic Delays: Pipeline construction will include Zeering Road from Quincy Road to Wellington, Quincy Road from Zeering Road to Sebastian, Monte Vista Ave. from Quincy to Berkeley. Lane closures will be in effect for work on Monte Vista Ave. and Zeering Road. Road closures will be in effect for Quincy Road (local traffic only). In addition, the Stanislaus Regional Water Authority (SRWA) will be installing pipeline to the City's terminal tank site on Berkeley Road (north of City limits), on E. Taylor Road between Berkeley and Quincy, and on Quincy Rd. to the City's terminal tank site located at 3500 N. Quincy Road. For more information, please visit Stanislaus Regional Water Authority and Turlock Water
Technical Contact: Project Manager, Stephen Fremming, ph: 209-668-5417, sfremming@turlock.ca.us
City Project #20-032 - Chemical System Upgrades Project at RWQCF
The Project consists of constructing the following components at the Regional Water Quality Control Facility: 1. Demolition of the existing Chlorine Gas disinfection system. 2. Installation of a new Sodium Hypochlorite disinfection system. 3. Demolition and installation of a new Coagulant chemical system. 4. Demolition and installation of a new Dechlorination system. 5. Additions and modifications to yard piping system. 6. Additions and modifications to electrical systems. 7. Additions and modifications to instrumentation systems. 8. Repair and reconstruction to existing facilities affected by the work and all work necessary to render the facility complete and operational.Construction Duration: Work for the following project is schedule to begin on or about Monday, June 6, 2022 and estimated to complete on or around Tuesday, November 1, 2022.
Contractor: Pacific Infrastructure Corporation
Traffic Delays: None
Technical Contact: Project Manager, Stephen Fremming, ph: 209-668-5417, sfremming@turlock.ca.us
City Project #20-027A - City Wide Chlorination
The work consists, in general, of: constructing new chlorination systems at fifteen (15) active wells and three (3) water storage tank/pumping stations within the City’s water system.Construction Duration: Work for the following project is schedule to begin on or about Wednesday, February 17, 2021 and estimated to complete on or around Wednesday, February 1, 2023.
Contractor: Clark Bros. Inc.
Traffic Delays: none
Technical Contact: Project Manager, Stephen Fremming, ph: 209-668-5417, sfremming@turlock.ca.us
City Project #21-018 - Lander Ave Rehabilitation between D St and SR-99
The work consists, in general of: Install curb, gutter, sidewalk, driveways, vertical median curb, landscaping, fire hydrants, street lights, pedestrian activated crossing system, pavement rehabilitation, striping and signage, traffic signal modifications, and other associated work.Construction Duration: Work for the following project is schedule to begin on or about Monday, August 22, 2022 and estimated to complete on or around Tuesday, January 31, 2023.
Contractor: George Reed
Traffic Delays: Lane Closures
Technical Contact: Project Manager, Randall Jones, 209-668-6021, rjones@turlock.ca.us
City Project #20-039 - Traffic Signal Synchronization on E. Monte Vista A
The work consists, in general of: Remove and replace traffic signal equipment and other associated work. The work includes all necessary labor, materials, tools, equipment and any incidentals needed to perform the improvements as shown on the contract plans.Construction Duration: Work for the following project is schedule to begin on or about Wednesday, February 1, 2023 and estimated to complete on or around Saturday, April 1, 2023.
Contractor: St. Francis Electric
Traffic Delays: None
Technical Contact: Project Manager, Randall Jones, 209-668-6021, rjones@turlock.ca.us
City Project #20-038 - Signal Coordination on W. Monte Vista Ave, Golden
The work consists, in general of: Remove and replace existing signal controllers, and remove and replace an existing detection camera system and other associated work. The work includes all necessary labor, materials, tools, equipment and any incidentals needed to perform the improvements as shown on the contract plans.Construction Duration: Work for the following project is schedule to begin on or about Wednesday, February 1, 2023 and estimated to complete on or around Saturday, April 1, 2023.
Contractor: St. Francis Electric
Traffic Delays: None
Technical Contact: Project Manager, Randall Jones, 209-668-6021, rjones@turlock.ca.us
City Project #19-51A - Columbia Pool Facility Demolition
The work consists, in general of: Demolition and removal of buildings, pool and pool equipment, concrete and concrete foundations, salvage fencing, install fencing and CMU wall, remove trees, and cap utilities and other associated work.Construction Duration: Work for the following project is schedule to begin on or about Wednesday, November 9, 2022 and estimated to complete on or around Tuesday, January 17, 2023.
Contractor: CVE Consulting Group
Traffic Delays: None
Technical Contact: Project Manager, Randall Jones, 209-668-6021, rjones@turlock.ca.us
City Project #20-013R - Water and Sewer Main Extensions Golden State Blvd
The work consists, in general, of: demolition, shoring utility potholing, traffic control, trenching, installation of water mains and lateral pipes, valves, fittings, fire hydrants, installation of sewer mains and manholes, paving, curb, gutter and sidewalk.Construction Duration: Work for the following project is schedule to begin on or about Tuesday, January 17, 2023 and estimated to complete on or around Wednesday, April 19, 2023.
Contractor: Rolfe Construction, Inc.
Traffic Delays: Pipeline construction will include Golden State Blvd. from Atherstone Road to about half a mile north of Taylor Road (near Price Ford of Turlock). Lane closures will be in effect on Golden State Blvd and Taylor Road.
Technical Contact: Project Manager, Janine Lee, 209-668-6035, jlee@turlock.ca.us
City Project #22-030 - Senior Center Sliding Glass Doors
Installation of sliding glass doors to replace existing accordion doors within the Senior Center located at 1191 Cahill St Turlock, CA 95380. An optional pre-bid meeting will be held on Thursday, March 23rd at 10:00 AM in the Senior Center located at 1191 Cahill St, Turlock, CA 95380.Construction Duration: Work for the following project is schedule to begin on or about Monday, July 17, 2023 and estimated to complete on or around Friday, July 28, 2023.
Contractor: Paul's Glass & Co.
Traffic Delays: None
Technical Contact: Project Manager, Charlotte Calvario, 209-668-6029, ccalvario@turlock.ca.us
City Project #22-037 - Fire Station No. 32 & 33 Reroof
Roof repair of Fire Station No. 32 (located at 791 S Walnut Rd, Turlock, CA 95380) and Fire Station No. 33 (located at 501 E Monte Vista Ave, Turlock, CA 95382). An optional pre-bid meeting will be held on Thursday, March 30, 2023 at 10:30 AM at Turlock Fire Station No. 33.Construction Duration: Work for the following project is schedule to begin on or about Monday, June 12, 2023 and estimated to complete on or around Friday, July 14, 2023.
Contractor: Pac Shield Roof Services, Inc.
Traffic Delays: None.
Technical Contact: Project Manager, Charlotte Calvario, 209-668-6029, ccalvario@turlock.ca.us